Phase 1.

  • Permit for preparatory works for phase 1, issued on 25.04.2019 № 351-02-00087/2019-07;
  • The issuance of a building permit for Phase 1, planned for May 2019.
  • The issuance of a permit for the commencement of works for the phase 1, planned for June 2019.

Phase 2.

  • Permit for preparatory works for phase 2, issued on 29.03.2019 № 351-02-00052/2019-07;
  • Building permit for Phase 2, issued on 16.05.2019 No. 351-02-00108/2019-07;
  • Permit for the commencement of works for Phase 2, issued on 27.05.2019 № 351-06-00378/2019-07.

Phase 3.

  • Permit for preparatory works for phase 3, issued on 11.04.2019, № 351-02-00066/2019;
  • Building Permit for Phase 3, Issued on 25.04.2019 № 351-02-00084/2019-07
  • Permit for the commencement of works for Phase 3, issued on May 20, 2019 № 351-06-00371/2019-07.

Phase 4.

  • The issuance of a permit for preparatory work for Phase 4, planned for July 2019.
  • The issuance of a building permit for Phase 4, planned for August 2019.
  • The issuance of a permit for the commencement of works for the phase 4, planned for August 2019.