About building permits

Phase 1. Permit for preparatory works for phase 1, issued on 25.04.2019 № 351-02-00087/2019-07; The issuance of a building permit for Phase 1, planned for May 2019. The issuance of a permit for the commencement of works for the phase …
Read More

The Energy Agency of the Republic of Serbia has adopted the decision on exemption of the gas pipeline, that will connect the gas transmission systems of Bulgaria and Hungary, from the regulations of the Third Energetic Package EU

On March 5th 2019, the Council of the Agency has adopted the request of the ’’Gastrans’’ company that the gas pipeline, which connects the gas networks of Bulgaria and Hungary through the territory of Serbia, should be exempt from the …